Comprehensive Guide

Construction Delay Analysis: Methods, Tools & Best Practices

A detailed comparison of every major delay analysis methodology — from the simplest observational approach to the most rigorous modelled-in-windows technique. Includes a decision matrix to help you choose the right method for your dispute.

By Constroma Team·30 min read

Introduction

Delay analysis is the process of determining the causes, effects, and responsibility for schedule delays on a construction project. Multiple methodologies exist, each with different strengths, weaknesses, data requirements, and levels of defensibility. This guide compares all five major methods and provides a framework for choosing the right approach.

1. As-Planned vs As-Built

The simplest delay analysis method. It compares the original baseline schedule against the actual project timeline to identify variances. Activities that finished later than planned are flagged as delayed, and the analyst examines the causes.

Strengths: Simple to perform, requires minimal data (just baseline and as-built records), good for initial assessment.

Weaknesses: Does not use CPM logic, cannot identify which delays affected the critical path, cannot reliably handle concurrent delay, and ignores the dynamic nature of the schedule over time.

2. Impacted As-Planned

An additive method that inserts delay events into the original baseline schedule and recalculates the CPM to project the impact on the completion date. Each delay event is modeled as a fragnet and added to the baseline.

Strengths: Uses CPM logic, can quantify the impact of individual delay events, relatively straightforward.

Weaknesses: Assumes the baseline schedule is reliable and realistic, does not account for actual progress or critical path shifts that occurred during the project, may overestimate or underestimate impacts.

3. Collapsed As-Built

A subtractive method that starts with the as-built schedule and removes delay events to determine the “but-for” completion date — what would have happened without those delays. Also known as the “but-for” method.

Strengths: Works from actual data, useful when baseline schedule is unreliable or unavailable, can demonstrate the impact of specific delay events.

Weaknesses: Requires constructing an accurate as-built schedule, results can vary depending on the order events are removed, may not handle concurrent delays well.

4. Time Impact Analysis (TIA)

The most widely accepted modelled approach. Each delay event is modeled as a fragnet and inserted into the schedule at the point in time when the delay occurred. CPM is recalculated before and after insertion to measure the impact.

Strengths: Measures individual event impacts using the schedule as it existed at the time, accounts for the dynamic critical path, can identify concurrent delays.

Weaknesses: Requires detailed schedule updates and delay event documentation, more time-consuming than simpler methods.

5. Windows Analysis (MIP 3.7)

The most rigorous methodology. Divides the project into analysis windows (typically aligned with schedule update periods) and performs TIA within each window. Delay events are processed chronologically within each window, and the results are compared against actual progress.

Strengths: Most defensible method, captures all critical path shifts and concurrent delays, produces window-by-window and cumulative results.

Weaknesses: Requires the most data and effort, may be disproportionate for low-value disputes.

Decision Matrix

CriterionRecommended Method
High-value dispute, full data availableMIP 3.7 (Windows TIA)
Schedule updates available, moderate complexityTime Impact Analysis
Limited schedule updates, good as-built recordsCollapsed As-Built
Baseline available but no updatesImpacted As-Planned
Preliminary assessment or low-value disputeAs-Planned vs As-Built

Conclusion

The choice of delay analysis method should be driven by the available data, the complexity of the dispute, and the level of rigor required. Where possible, use the most rigorous method the data supports. Constroma automates TIA and Windows Analysis, making the most defensible methods accessible without weeks of manual effort.

Automate Your Delay Analysis

Run TIA and Windows Analysis automatically with Constroma.

Start Free Trial

Frequently Asked Questions

What are the main delay analysis methods?
The main methods are: As-Planned vs As-Built (observational comparison), Impacted As-Planned (additive modeling on baseline), Collapsed As-Built (subtractive modeling on as-built), Time Impact Analysis (fragnet insertion with CPM recalculation), and Windows Analysis / MIP 3.7 (TIA within defined time periods). Each has different data requirements, rigor levels, and applicability.
Which delay analysis method is most defensible?
Windows Analysis (MIP 3.7) using Time Impact Analysis within each window is generally considered the most rigorous and defensible method. It accounts for critical path shifts, concurrent delays, and the actual schedule context at the time of each delay. However, it requires the most data and analytical effort.
What is the difference between additive and subtractive methods?
Additive methods (like TIA and Impacted As-Planned) add delay events to a schedule and measure the impact. Subtractive methods (like Collapsed As-Built) start with the actual outcome and remove delay events to determine the "but-for" completion date. Both approaches should produce similar results if applied correctly, but they can differ when delays interact.
How does concurrent delay affect method selection?
Concurrent delay — where multiple delay events affect the critical path simultaneously — is best identified using Time Impact Analysis within windows (MIP 3.7). Simpler methods like As-Planned vs As-Built cannot reliably identify or apportion concurrent delays, making them less suitable for disputes involving overlapping causes.
What is float ownership and why does it matter?
Float ownership determines who benefits from scheduling flexibility. If float "belongs to the project" (the most common position), neither party can claim exclusive use of it. If a contractor uses float to absorb a delay, the employer cannot later claim that float for their own delays. The SCL Protocol recommends that float should be available to the project and not owned by either party.